Board Information

To continue to promote and encourage renewable generation resources, the Board voted to accept generated capacity up to 1.5% of Salem Electric’s single-hour peak load (1,368 kW) from net-metered generation sources. 

Adjustments to the 2022 budget were approved as presented.

General Manager's Report

A preliminary design for the facilities improvement project has been completed and bids from local contractors are being collected to determine preliminary cost estimates.

Initial research shows that a Pre-Pay rate could benefit members. Additional data will be collected as part of the Board’s five-year strategic plan.